Home » Case studies » C228 – Future Growth Project
Future Growth Project
| Ref | C228 |
|---|---|
| Location | Kazakhstan |
| Year | 2015 |
| Application | Metering, Prover, Sampling |
| Contractor | Kazakh PJV |
| End user | TCO, Tengizchevroil |
Products & services
- LACT Metering Package
- Prover
- Sample Shelter
Scope Overview
OGS commenced work on the project in 2015. The initial scope included Metering skid for maximum capacity of 4650m³/hr with three metering runs, a bi-directional prover, and a sampling system. The equipment was procured and manufacturing had begun; however, in 2019 the client increased the required capacity to 9160 m³/h.
As a result, the entire project was re-engineered to meet the new throughput requirement, while complying with strict pressure drop limitations and maximising the reuse of equipment and materials already purchased during the first project phase. During the design phase, it was necessary to address the requirements of all stakeholders and to harmonise the project specifications with the applicable standards of the Republic of Kazakhstan.
The final system configuration included:
- A metering skid comprising six metering runs with turbine meters
- A bi-directional prover
- An analyser house with pump skid
- A Metering Control System
Throughout installation, commissioning, and start-up, OGS provided comprehensive site services to ensure the successful execution of the project.
In August 2025, the LACT system successfully passed type approval testing and received the required metrological certification. In September 2025, the system was successfully handed over for operation.